桥梁顶推法施工研究现状及发展趋势

赵人达, 张双洋

中国公路学报 ›› 2016, Vol. 29 ›› Issue (2) : 32-43.

PDF全文下载(1072 KB)
PDF全文下载(1072 KB)
中国公路学报 ›› 2016, Vol. 29 ›› Issue (2) : 32-43.
桥梁工程

桥梁顶推法施工研究现状及发展趋势

  • 赵人达, 张双洋
作者信息 +

Research Status and Development Trend on Incremental Launching Construction of Bridges

  • ZHAO Ren-da, ZHANG Shuang-yang
Author information +
文章历史 +

摘要

为了促进桥梁顶推法施工技术的发展,对目前桥梁建设中广泛应用的顶推法施工技术进行了综述,着重介绍和总结了顶推施工中导梁参数的确定方法、梁体施工精度对顶推过程产生的影响、梁体顶推过程受力分析、顶推过程中局部受力分析及改善措施、顶推法施工控制等研究成果。研究结果表明:多点顶推过程中的局部受力状态、施工误差对梁体局部受力的影响以及下部结构采用拉索加固法时的索力优化问题仍较为突出;研究指出了近几年在中国发展起来的步履式顶推施工法所存在的一些问题,探讨了今后顶推法施工的发展趋势。

Abstract

In order to promote the development of bridge incremental launching construction technology, the technology widely used in current bridge construction was reviewed. The method for determining key parameters of the launching nose, influence of beam construction accuracy on incremental launching process, force analysis of incremental launching process, force analysis of local stress and improvement measures and incremental launching construction control were introduced and summarized. The results show that the influences of local stress status in the process of multipoint incremental launching and construction error on bearing beam, and the optimization problem of cable tension when cable reinforcement method is used in substructure are still prominent. Finally, some existing problems on walking type incremental launching construction at present in China are mentioned and the further development trend of incremental launching construction is investigated.

关键词

桥梁工程 / 顶推法施工 / 综述 / 导梁 / 施工控制

Key words

bridge engineering / incremental launching construction / review / launching nose / construction control

引用本文

导出引用
赵人达, 张双洋. 桥梁顶推法施工研究现状及发展趋势[J]. 中国公路学报, 2016, 29(2): 32-43
ZHAO Ren-da, ZHANG Shuang-yang. Research Status and Development Trend on Incremental Launching Construction of Bridges[J]. China Journal of Highway and Transport, 2016, 29(2): 32-43
中图分类号: U445.462   

参考文献

[1] 邵厚坤,周以诚,罗西园.用顶推法施工的狄家河桥[J].铁道学报,1979,1(2):63-78. SHAO Hou-kun,ZHOU Yi-cheng,LUO Xi-yuan.Construction of Dijiahe Bridge by Launching Method[J].Journal of the China Railway Society,1979,1(2):63-78.
[2] 李传习,邹桂生.法国米约高架桥-7塔斜拉桥的设计与施工[J].世界桥梁,2005(4):18-20. LI Chuan-xi,ZOU Gui-sheng.Design and Construction of Seven-pylon Cable-stayed Bridge of Millau Viaduct in France[J].World Bridges,2005(4):18-20.
[3] 赵永峰.梁济运河大桥钢箱梁顶推施工数值仿真技术研究[D].济南:山东大学,2010. ZHAO Yong-feng.Numerical Simulation Technology Research on Steel-box Girder Incremental Launching Construction of Liangji Canal Bridge[D].Jinan:Shandong University,2010.
[4] 张晓东.桥梁顶推施工技术[J].公路,2003(9):45-51. ZHANG Xiao-dong.Incremental Launching Construction Technology of Bridge[J].Highway,2003(9):45-51.
[5] 王磊,刘家锋.顶推架设沃克斯高架桥[J].铁道标准设计,2001,21(12):7-8. WANG Lei,LIU Jia-feng.Incremental Launching Erection of Vaux Viaduct[J].Railway Standard Design,2001,21(12):7-8.
[6] 王俊.大跨度变曲率竖曲线钢箱梁顶推施工仿真优化[D].长沙:长沙理工大学,2009. WANG Jun.Simulation and Optimization for Long-span Changing Curvature Vertical Curve Steel-box Girder Bridge Constructed by Incremental Launching Method[D].Changsha:Changsha University of Science & Technology,2009.
[7] 龚志刚.顶推重量9000 t的墨西哥恰帕斯连续钢箱梁桥[J].世界桥梁,2004(4):27. GONG Zhi-gang.Mexico Chiapas Continuous Steel-Box Girder Bridge with Incremental Launching 9000 t[J].World Bridges,2004(4):27.
[8] 汤俊生.PC梁顶推施工技术的回顾与展望[J].桥梁建设,1996(1):11-14. TANG Jun-sheng.Review and Prospect for Incremental Launching Technique for Prestressed Concrete Girder[J].Bridge Construction,1996(1):11-14.
[9] 李永铎.都市区及区域交通现代化[M].合肥:安徽科学技术出版社,2005. LI Yong-duo.Transportation Modernization of Urban and Regions[M].Hefei:Anhui Science & Technology Publishing House,2005.
[10] 刘杰.大跨度钢箱梁斜交顶推结构受力特性与施工控制技术研究[D].长沙:长沙理工大学,2006. LIU Jie.Research on Key Technologies of Construction Control & Mechanics Characters of Long-span Steel-box Girder Which Constructed by Incremental Launching Method[D].Changsha:Changsha University of Science & Technology,2006.
[11] 邵长宇.九堡大桥组合结构桥梁的技术构思与特色[J].桥梁建设,2009(6):42-45. SHAO Chang-yu.Technical Consideration and Features of Composite Structure Bridge of Jiubao Bridge in Hangzhou[J].Bridge Construction,2009(6):42-45.
[12] 傅琼阁,胡义新,姜保宋.九堡大桥主桥顶推施工控制分析[J].施工技术,2010,39(增):343-347. FU Qiong-ge,HU Yi-xin,JIANG Bao-song.Control Analysis of Push Construction on Main Bridge of Jiubao Bridge[J].Construction Technology,2010,39(S):343-347.
[13] 牛辉.空间拱肋组合桥梁顶推施工技术研究[D].杭州:浙江大学,2012. NIU Hui.Study of Incremental Launching Technology of Space Arch Combination Bridges[D].Hangzhou:Zhejiang University,2012.
[14] 李冲杰.跨铁路PC箱梁桥顶推施工安全监控及关键技术研究[D].成都:西南交通大学,2015. LI Chong-jie.Research on the Key Technologies and Safety Monitoring of Prestressed Concrete-box Shaped Girder Bridge Across Railway by Incremental Launching Construction[D].Chengdu:Southwest Jiaotong University,2015.
[15] 谢祺.步履式顶推施工工艺对钢箱梁局部受力的分析研究[D].成都:西南交通大学,2015. XIE Qi.Local Stress Analysis of Steel-box Girder Which Constructed by the Walking-type Incremental Launching Technology[D].Chengdu:Southwest Jiaotong University,2015.
[16] 王彪.钢混组合梁步履式顶推横向偏位产生原因及纠偏对策研究[D].成都:西南交通大学,2015. WANG Biao.Local Stress Analysis of Steel-box Girder Which Constructed by the Walking-type Incremental Launching Technology[D].Chengdu:Southwest Jiaotong University,2015.
[17] ROSIGNOLI M.Nose-deck Interaction in Launched Prestressed Concrete Bridges[J].Journal of Bridge Engineering,1998,3(1):21-27.
[18] BEANEY N J,MARTIN J M.Design and Construction of the Dornoch Firth Bridge[J].Proceedings of ICE-Transport,1993,100(3):145-156.
[19] ROSIGNOLI M.Prestressing Schemes for Incrementally Launched Bridges[J].Journal of Bridge Engineering,1999,4(2):107-115.
[20] 田仲初,张华平.顶推施工中导梁的合理配置[J].世界桥梁,2005(4):41-43,47. TIAN Zhong-chu,ZHANG Hua-ping.Reasonable Arrangement of Launching Nose in Incremental Launching Construction[J].World Bridges,2005(4):41-43,47.
[21] 上官兴.连续梁顶推工艺的新构思[J].东北公路,1994(4):71-82. SHANGGUAN Xing.A New Idea About Incremental Launching Technology of Continuous Bridge[J].Northeast Highway,1994(4):71-82.
[22] 董创文,李传习.连续梁顶推导梁合理参数的确定方法[J].公路交通科技,2010,27(9):55-62. DONG Chuang-wen,LI Chuan-xi.Method for Determination of Reasonable Parameters of Launching Nose for Continuous Beam[J].Journal of Highway and Transportation Research and Development,2010,27(9):55-62.
[23] 刘树爱.顶推施工阶段内力分析及临时结构设计[J].石家庄铁道学院学报,1998,11(增):1-5. LIU Shu-ai.Structural Analysis and Construction Design of Prestressed Concrete Continuous Beam at Construction Stage[J].Journal of Shijiazhuang Railway Institute,1998,11(S):1-5.
[24] 王卫锋,林俊锋,马文田.桥梁顶推施工导梁的优化分析[J].工程力学,2007,24(2):132-138. WANG Wei-feng,LIN Jun-feng,MA Wen-tian.Optimum Analysis of Launching Nose During Incremental Launching Construction of Bridge[J].Engineering Mechanics,2007,24(2):132-138.
[25] 田启军,陈湘林.顶推施工中导梁的应用与锚固措施的优化[J].中外公路,2003,23(6):38-40. TIAN Qi-jun,CHEN Xiang-lin.Application of Launching Nose and Optimization of Anchoring Method in Incremental Launching Construction[J].Journal of China & Foreign Highway,2003,23(6):38-40.
[26] 赵志平.桥梁顶推施工的精度探讨[J].桥梁建设,1994(2):70-73. ZHAO Zhi-ping.Research on Accuracy of Incremental Launching Construction of Bridge[J].Bridge Construction,1994(2):70-73.
[27] 王卫锋,林俊峰,马文田.顶推施工中临时墩位置对梁体制造误差的影响[J].华南理工大学学报:自然科学版,2006,34(9):76-79,89. WANG Wei-feng,LIN Jun-feng,MA Wen-tian.Effect of Location of Temporary Pier in Incremental Launching Construction on the Manufacture Error of Girder[J].Journal of South China University of Technology:Natural Science Edition,2006,34(9):76-79,89.
[28] 周季湘.等截面连续梁桥顶推施工的受力分析[J].公路,1994(11):20-23. ZHOU Ji-xiang.Force Analysis of Continuous Beam with Constant Section During Incremental Launching[J].Highway,1994(11):20-23.
[29] SASMAL S,RAMANJANEYULU K,SRINIVAS V,et al.Simplified Computational Methodology for Analysis and Studies on Behavior of Incrementally Launched Continuous Bridges[J].Structural Engineering and Mechanics,2004,17(2):245-266.
[30] 梁爱斌,王春生,徐岳.采用MATLAB语言开发连续梁桥顶推施工结构分析程序[J].交通与计算机,2000,18(5):57-61. LIANG Ai-bin,WANG Chun-sheng,XU Yue.Analysis Program of Incremental Launching Construction Structure for Continuous Girder Bridge with MATLAB[J].Traffic and Computer,2000,18(5):57-61.
[31] 邵斌磊,徐荣桥.钢混组合梁的顶推施工过程分析[C]//中国力学学会.第19届全国结构工程学术会议论文集.北京:工程力学杂志社,2010:477-481. SHAO Bin-lei,XU Rong-qiao.Analysis of Steel Concrete Composite Beam During Incremental Launching[C]//The Chinese Society of Theoretical and Applied Mechanics.Proceedings of the 19th Annual National Academic Conference on Structural Engineering(Ⅱ).Beijing:Engineering Mechanics Press,2010:477-481.
[32] 张晔芝,谢晓慧.铁路特大桥钢箱梁顶推过程受力分析及改善方法[J].中国铁道科学,2009,30(3):21-26. ZHANG Ye-zhi,XIE Xiao-hui.The Mechanical Behaviors and Improvement Measures of Railway Grand Bridge During Incremental Launching of the Steel-box Girder[J].China Railway Science,2009,30(3):21-26.
[33] 尹超裕.大跨径钢槽梁顶推局部应力分析及现场监测[D].长沙:长沙理工大学,2012. YIN Chao-yu.Analysis on Local Stress of Long-span Steel Racks Beam Incremental Launching Construction and Field Monitoring[D].Changsha:Changsha University of Science & Technology,2012.
[34] 王文雷,冯德飞,卢文良.顶推法施工中钢箱梁在滑道处的局部应力分析[J].北京交通大学学报,2006,30(增):190-193. WANG Wen-lei,FENG De-fei,LU Wen-liang.Local Stress Analysis of Steel Box Beam Close to Sliding Path by Incremental Launching Method[J].Journal of Beijing Jiaotong University,2006,30(S):190-193.
[35] 苏魁.钢箱梁斜拉桥顶推施工关键问题[D].上海:同济大学,2006. SU Kui.The Research of Key Problems in the Incremental Launching of Cable-stayed Bridge with Steel Box Girder[D].Shanghai:Tongji University,2006.
[36] ROSIGNOLI M.Bridge Launching[M].London:Thomas Telford Publishing,2002.
[37] 李新华.大跨度钢箱梁斜拉桥顶推施工中关键技术研究[D].成都:西南交通大学,2013. LI Xin-hua.Research on the Key Technologies of Incremental Launching of Long-span Cable-stayed Bridge with Steel Box Girder[D].Chengdu:Southwest Jiaotong University,2013.
[38] ZHANG Ye-zhi,LUO Ru-deng.Patch Loading and Improved Measures of Incremental Launching of Steel Box Girder[J].Journal of Constructional Steel Research,2012,68(1):11-19.
[39] 赵博.双线铁路2×90 m叠合拱桥钢箱梁顶推方案的研究[D].长沙:中南大学,2009. ZHAO Bo.Research of Incremental Launching Method of Steel-box Girder of 2×90 m Span Stacked Arch Bridge with Two Railway Lines[D].Changsha:Central South University,2009.
[40] 宋延旭.顶推施工阶段钢箱梁桥受力性能研究[D].北京:北京交通大学,2010. SONG Yan-xu.Study on Structural Performance of Steel Box Girder Bridge During the Incremental Launching Construction Stage[D].Beijing:Beijing Jiaotong University,2010.
[41] 周叶飞.变曲率竖曲线钢箱梁顶推受力特性及施工控制技术研究[D].长沙:长沙理工大学,2010. ZHOU Ye-fei.Research on Key Technologies of Construction Control & Mechanics Characters of Multisection Curved Steel-box Grider Bridge which Constructed by Incremental Launching Method[D].Changsha:Changsha University of Science & Technology,2010.
[42] 田仲初,陈耀章,赵利平,等.连续钢梁顶推过程局部接触分析及改善措施[J].长安大学学报:自然科学版,2012,32(4):44-50. TIAN Zhong-chu,CHEN Yao-zhang,ZHAO Li-ping,et al.Local Contact Analysis and Improvement Measures of Continuous Steel Girder Incremental Launching[J].Journal of Chang'an University:Natural Science Edition,2012,32(4):44-50.
[43] 崔清强.复杂预制线形钢箱梁顶推计算分析[J].桥梁建设,2009(6):50-53. CUI Qing-qiang.Calculation and Analysis of Incremental Launching Erection of Prefabricated Steel Box Girders Having Complicated Geometry[J].Bridge Construction,2009(6):50-53.
[44] 刘丽萍,王应良.南京长江第二大桥南汊主桥流线型薄壁扁平钢箱梁分析的新方法[J].公路交通科技,2004,21(7):51-54. LIU Li-ping,WANG Ying-liang.New Analysis Methods of Nanjing Yangtze River Second Bridge Streamline Flat Thin-walled Box Girder[J].Journal of Highway and Transportation Research and Development,2004,21(7):51-54.
[45] 徐伟,李智,张肖宁.子模型法在大跨径斜拉桥桥面结构分析中的应用[J].土木工程学报,2004,37(6):30-34. XU Wei,LI Zhi,ZHANG Xiao-ning.Application of Submodeling Method for Analysis for Deck Structure of Diagonal Cable-stayed Bridge with Long Span[J].China Civil Engineering Journal,2004,37(6):30-34.
[46] ZHANG H,DESROCHES R.Experimental and Analytical Studies on a Streamlined Steel Box Girder[J].Journal of Constructional Steel Research,2010,66(7):906-914.
[47] 胡志坚,孔祥韶,吴卫国.九堡大桥顶推施工模型试验[J].公路交通科技,2012,29(1):91-96. HU Zhi-jian,KONG Xiang-shao,WU Wei-guo.Model Test of Construction of Jiubao Bridge with Incremental Launching[J].Journal of Highway and Transportation Research and Development,2012,29(1):91-96.
[48] 张治成,匡勇江,韩晗,等.顶推法槽型钢梁在局部荷载作用下的极限承载力[J].结构工程师,2011,27(6):59-65. ZHANG Zhi-cheng,KUANG Yong-jiang,HAN Han,et al.Ultimate Bearing Capacity of Steel U-Girders Under Local Load in Incremental Launching Method[J].Structural Engineers,2011,27(6):59-65.
[49] 周嫚,王福敏,王鹏,等.曲线预应力连续梁桥悬拼施工误差敏感性分析[J].重庆交通大学学报:自然科学版,2011,30(6):1306-1310. ZHOU Man,WANG Fu-min,WANG Peng,et al.Sensitivity Analysis on Error in Cantilever Erection of Curve Prestressed Continuous Girder Bridge[J].Journal of Chongqing Jiaotong University:Natural Science,2011,30(6):1306-1310.
[50] 关冀,张雪松,周莹.某连续刚构桥底板崩裂的施工误差敏感性分析[J].黑龙江科技信息,2010(8):234-235. GUAN Ji,ZHANG Xue-song,ZHOU Ying.Sensitivity Analysis of Construction Error of Bottom Plate Failure Mechanism on One Continuous Rigid Frame Bridge[J].Heilongjiang Science and Technology Information,2010(8):234-235.
[51] 郝超.大跨度钢斜拉桥施工误差调整方法研究[J].浙江大学学报:工学版,2003,37(3):310-313. HAO Chao.Study on Construction Error Adjustment Method of Long-span Steel Cable-stayed Bridge[J].Journal of Zhejiang University:Engineering Science,2003,37(3):310-313.
[52] 刘晓霞,邱琼海,张建红,等.东海大桥8×50 m顶推箱梁施工技术[J].世界桥梁,2004(增):66-69,81. LIU Xiao-xia,QIU Qiong-hai,ZHANG Jian-hong,et al.Construction Techniques for 8×50 m Incrementally Launched Box Girders of Donghai Bridge[J].World Bridges,2004(S):66-69,81.
[53] 向中富.桥梁施工控制技术[M].北京:人民交通出版社,2001. XIANG Zhong-fu.Bridge Construction Control Technique[M].Beijing:China Communications Press,2001.
[54] 徐建富,余毅.多跨刚构连续梁组合桥上部结构施工监控[J].世界桥梁,2011(4):33-35. XU Jian-fu,YU Yi.Construction Monitoring and Control of Superstructure of Multi-span Rigid-frame and Continuous Girder Hybrid Bridge[J].World Bridges,2011(4):33-35.
[55] 张玉平,董创文.江东大桥双塔单跨空间主缆自锚式悬索桥的施工控制[J].公路交通科技,2010,27(7):76-82. ZHANG Yu-ping,DONG Chuang-wen.Construction Control of Self-anchored Suspension Bridge with Two Pylons and Single Span Spatial-cables in Jiangdong Bridge[J].Journal of Highway and Transportation Research and Development,2010,27(7):76-82.
[56] 许明雷,罗力军.排调河一号特大桥中跨合龙顶推控制[J].桥梁建设,2011(4):79-82. XU Ming-lei,LUO Li-jun.Control of Pushing for Closure of Central Span of Paidiao River Bridge No.1[J].Bridge Construction,2011(4):79-82.
[57] 周绪红,吕忠达,狄谨,等.大跨径简支转连续箱梁桥的线性观测与控制[J].中国公路学报,2007,20(3):54-59. ZHOU Xu-hong,LU Zhong-da,DI Jin,et al.Line Shape Observation and Control of Simple-supported-to-continuous Long-span Box Girder Bridges[J].China Journal of Highway and Transport,2007,20(3):54-59.
[58] 董创文,李传习,王琛.考虑相位变化及组拼高程误差的顶推梁体无应力线形的实现[J].土木工程学报,2013,46(8):74-82. DONG Chuang-wen,LI Chuan-xi,WANG Chen.Achieving Unstressed Geometry of Incrementally Launched Girders Considering Phase Shift and Elevation Deviation During Assembly Stage[J].China Civil Engineering Journal,2013,46(8):74-82.
[59] 刘宏文.五里亭大桥主桥连续箱梁预制拼装顶推施工技术[J].铁道建筑技术,2004(4):11-13. LIU Hong-wen.Prefabrication,Assembly,and Thrusting Erection Technology for the Continuous Box Beam of Wuliting Bridge[J].Railway Construction Technology,2004(4):11-13.
[60] 王世峰,陈超华,孙晓伟.多变竖曲线钢槽梁拼装及顶推施工技术[J].中外公路,2012,32(3):237-241. WANG Shi-feng,CHEN Chao-hua,SUN Xiao-wei.Changable Vertical Curve Groove Steel Beam Assembly and Incremental Launching Technology[J].Journal of China & Foreign Highway,2012,32(3):237-241.
[61] 阙水杰,岳青,严和仲.厦漳跨海大桥钢箱梁斜拉桥中、边跨合龙施工技术[J].世界桥梁,2013,41(4):21-25. QUE Shui-jie,YUE Qing,YAN He-zhong.Construction Technique for Central Span and Side Span Closure of Steel Box Girder Cable-stayed Bridge of Xiamen-Zhangzhou Sea-crossing Bridge[J].World Bridges,2013,41(4):21-25.

基金

国家自然科学基金项目(51208431,51308468);铁道部科技研究开发计划项目(2010G018-A-1)